Quarter MW solar power plant installation on the roofs of the higher institute of sciences and technology in Alasaba
Main Article Content
Abstract
In recent years, public organizations have actively participated in the installation of solar power plants (SPPs) in Libya, in addition to the private sector. In the study, SPP installation on the roofs of five institute buildings within the Higher Institute of Sciences and Technology was planned, and PVsyst software was used for simulation. The findings show that SPP provides about 35.17% of the Institute’s electrical energy needs after installation, with a return on investment of about 4.65 years. As a result, after the amortization period has passed, this system will still be usable within the panels’ warranty duration.